Posts

Showing posts from August, 2024

Utility-Scale Hybrid Generation: The 28 MW Niger State Power Project

Image
Utility-Scale Hybrid Generation · Project Record The 28 MW Niger State Power Project International Consolidated Contractors Offshore SAL Ltd  |  Niger State, Nigeria  |  Nigeria Electrification Project International Consolidated Contractors Offshore SAL Ltd designed, supplied, installed, tested and commissioned a 28 MW hybrid power generation project in Niger State . The Rural Electrification Agency certified commissioning on 10 May 2024 , for a total contract value of US$45,242,000 , with the works fully executed between 15 May 2023 and 10 May 2024. The contract was awarded on 20 April 2023 under reference REA-NEP/C/GO/IS/RFP/105/21A, following a proposal dated 1 March 2023, and the Agency issued its certificate on 19 July 2024. This is the largest single generation contract in the company’s Nigerian portfolio by value, and the only one connecting at 132 kV into the national transmission network . ...